| Activity |
Date or Dates Planned |
Status |
| Ground Breaking
Ceremony |
Tuesday, May 1st |
Completed |
| Site
Excavation |
May
15th - May 16th |
Completed |
| Rough
Grade |
May
16th - 18th |
Completed |
| Back Fill Aggregate
for Base Course |
May
16th - May 18th |
Completed |
| Shed Foundation
Set |
May
15th |
Completed |
| Shed Foundation
Poured |
May
19th |
Completed |
| Shed
Construction |
May
21st - June 6th |
On-Going |
| Bioretention Cell
Excavated |
May
15th |
Completed |
| Bioretention Cell -
Aggregate, Fabric, Top Soil |
May 16th, June 2nd |
Competed |
| Bioretention Cell -
Remainder of Top Soil |
May 21st - 28th, June 2nd |
Completed |
| Rainwater Harvesting
Tank - Placing |
May
17th |
Completed |
| Final Grade
|
May 21st - 22rd |
Completed |
| Pervious Concrete
Prep |
May
24th |
Completed |
| Pervious Concrete
Installation & Finishing |
May
25th |
Completed |
| Porous Paver
Installation |
June
4th - 6th |
Completed |
| Pervious Asphalt
Installation |
June
4th - 6th |
Completed |
| Landscape Prep
(Topsoil, Irrigation, Mulch) |
May
29th - June 8th |
Completed |
| Planting |
June
9th, 10th |
Completed |
| Extruded Curb
Installation |
June
7th |
Completed |
| Parking Stripe
Painting |
June
7th |
Completed |
| |
|
|
| |
|
|
| |
|
|