Low Impact Development Showcase Project
Kitsap Home Builders Foundation * 5251 Auto Center Way * Bremerton * WA
Photographs During Construction
Click on Link in Left Column for Photos
Grubbing, Site Excavation, Aggregate and Rough Grade
May 15th through May 18th
New Shed Foundation
May 16th through May 19th
Bioretention Cell - Excavaion and Fill
May 16th
Pervious Concrete Sidewalks (City of Bremerton)
May 18th
Rainwater Harvesting Containter
May 17th & 18th
Final Grade of Parking Lot
May 21st, 22nd
Pervious Concrete Prep
May 24th
Pervious Concrete Pour & Finish
May 25th
Porous Paver Prep, Installation and Finishing
June 4th
New Shed Slab
June 2nd
New Shed Construction
June 2nd - June 10th
Pervious Asphalt Installation
June 5th
Amending Soils
June 2nd - June 8th
Landscaping - Prep, Dirp Irrigation, Planting and Mulch
June 2nd - June 10th
Return to Main Page